View Details

Return to the Bids Homepage

Bid Classification: 
Construction
Bid Type:  RFP
Bid Number:  PRC002071
Bid Name:  Elevator Upgrades
Bid Status:  Closed
Published Date:  Mon Jan 27, 2020 2:00:00 PM (EST)
Bid Closing Date:  Tue Feb 25, 2020 2:00:00 PM (EST)
Question Deadline:  Tue Feb 11, 2020 4:00:00 PM (EST)
Time-frame for delivery or the duration of the contract:  Refer to project document
Negotiation Type:  Refer to project document
Condition for Participation:  Refer to project document
Electronic Auctions:  Not Applicable
Language for Bid Submissions:  English unless specified in the bid document
Submission Type:  Hard Copy Submissions Only
Submission Address:  300 City Centre Drive, Ground Floor, Mississauga ON L5B 3C1
Public Opening:  Yes
Public Opening Address:  300 City Centre Drive, Mississauga ON L5B 3C1
Description: 

Carkson Community Center:

  • Elevator Upgrades:
  • Selective demolition and safe removal from site of existing vertical lift equipment,  and all associated components, piping, pumps, etc.;
  • General Contractor to ensure equipment procurement shop drawing is immediately expedited upon award, decommissioning/ demolition of existing equipment to only proceed after equipment delivery and installation timeline is confirmed;
  • All components of new LULA elevator be received on site, transported to the area of work, and assembled in place by qualified TSSA certified installer;
  • Architectural and Structural modification of existing shaft to accommodate to the new LULA elevator.
  • The overall scope includes but is not limited to all associated Mechanical, Electrical, security, controls and building fire controls.
  • Special Site requirements:
  • Coordinate activities by separate contractor for roof top units craning. Site access closed/impacted for upto one (1) day in April 2020. Final date to be coordinated during construction.

Huron Park Community Center:

  • Elevator Upgrades (north and south):
  • Selective demolition and safe removal from site of existing vertical lift equipment,  and all associated components, piping, pumps, etc;
  • General Contractor to ensure equipment procurement and shop drawing is immediately expedited upon award, decommissioning/ demolition of existing equipment to only proceed after equipment delivery and installation timeline is confirmed;
  • All components of new LULA elevator be received on site, transported to the area of work, and assembled in place by qualified TSSA certified installer;
  • Architectural and Structural modification of existing shaft to accommodate to the new LULA elevator.
  • Modification to existing exit stair adjacent to north elevator.
  • Modification to existing HM doors and screens.
  • The overall scope includes but is not limited to all associated Mechanical, Electrical, security, controls and building fire controls.
  • Special Site requirements:
  • Existing modbit roof system around the south elevator shaft recently installed by Triumph, contact Leandro Pedra 416 534 8877 cell: 416 554 1725 and still under warranty. All repairs and modification to this roof be done by Triumph to maintain existing roof system warranty.
  • Refer to drawings for details on phased execution of the two north and south elevators for work on this site.

Erin Mills Twin Arena:

  • Elevator Upgrades:
  • Selective demolition and safe removal from site of existing vertical lift equipment,  and all associated components, piping, pumps, etc.;
  • General Contractor to ensure equipment procurement and shop drawing is immediately expedited upon award, decommissioning/ demolition of existing equipment to only proceed after equipment delivery and installation timeline is confirmed;
  • All components of new LULA elevator be received on site, transported to the area of work, and assembled in place by qualified TSSA certified installer;
  • Architectural and Structural modification of existing shaft to accommodate to the new LULA elevator.
  • Entry Vestibule and Observation space:
  • Selective demolition and safe removal existing HM swing doors at front vestibule and at the two rinks, removal of upper level hollow metal screens.
  • New Automatic aluminum sliding entrance door system, along with swing doors.
  • New sprinkler protected hollow metal glass screens.
  • New floor finishes where indicated along with entrance foot grille.
  • The overall scope includes but is not limited to all associated Mechanical, Electrical, security, controls and building fire controls.
  • Special Site requirements:
  • Refer to drawings for details on phased execution of this work.
  • Coordinate activities by separate contractor carrying out lighting upgrades on site.

The overall scope for all three facilities includes but is not limited to all associated Mechanical, Electrical, security, controls and building fire controls (sprinkler rework, fire alarm tie in etc.,)..

Bid Document Access:  Bid document preview, bid opportunity, and award notices are available on the site free of charge. Suppliers are not required to register for a bid opportunity prior to previewing unsecured bid documents. Please note, some documents may be secured and you will be required to register for the bid to download and view the documents. To obtain an unsecured version of the bid document and/or to participate in this opportunity, an annual or a per bid fee must be paid (annual fee - $439.90, per bid fee - $132.04).
Trade Agreement Description:  Show Trade Agreement Description [+]
CETA
CFTA
Categories:  Show Categories [+]
  • Consulting Services - Professional Services
    • Architectural
  • Building Services
    • Elevator

Meeting Locations

The following are the meeting times and locations for the bid:


This information is only available to invited bidders and registered plan takers. To view this information you must login to your account.
This information is only available to invited bidders and registered plan takers. To view this information you must login to your account.
This information is only available to invited bidders and registered plan takers. To view this information you must login to your account.

Bids Submitted

The following are the unofficial bid results

No submitted bids...

Plan Takers

The following are the plan takers for the bid:

There are no plan takers for this bid.
This information is only available to invited bidders and registered plan takers. To view this information you must login to your account.